The KC-10 TS Pinnacle team completed Boom Operator Trainer (BOT #2) modification ahead of schedule and with ZERO test discrepancy reports (TDRs) after acceptance testing. More testing with the government representatives is scheduled for the week of February 4th, but once complete we hope for successful completion of this phase of the project by getting the Material Inspection and Receiving Report (DD-250) signed.

A huge Thank You for a Job Well Done! goes to Andrew Hand, Aaron Harris, Kyle Knapp, and Cody Fisher for all the great work on the KC-10 BOT program on-site and back at home. Having a training device modification accepted with ZERO discrepancy reports is a testimony to their hard work and commitment!